X and Y can finish a piece of work in 30 days. Six days they work together and then X quits the work. Y takes 32 days to finish the work. Calculate how many days Y take to complete the piece of work: (1) 32 days (2) 10 days (3) 30 days (4) 40 days
Solution:
By using the unitary method, we can calculate the work done by X and Y in a day.
To calculate the total work done, we will be taking the LCM of 30 and 32.
Let's write down the prime factorization of 30 and 32.
30 = 2 × 3 × 5
32 = 2 × 2 × 2 × 2 × 2
LCM(30, 32) = 2 × 2 × 2 × 2 × 2 × 3 × 5 = 480
Thus, total work done is 480 units
Given: X and Y together complete the work in 30 days
Units of work done per day by X and Y together is (X + Y ) = 480/30
(X + Y) = 16 units/day
According to the question,
efficiency of (X + Y) working for 6 days + efficiency of Y working for 32 days completes 480 units of work
(16 × 6) + (Y × 32) = 480
96 + 32Y = 480
32Y = 480 - 96
Y = 384 / 32
Y = 12
Thus, Y can complete 12 units/day
Time taken by Y to complete the whole work = Total work / 12
= 480/ 12 = 40
Thus, Option (4) 40 days, is the total number of days taken by Y to complete the piece of work alone.
X and Y can finish a piece of work in 30 days. Six days they work together and then X quits the work. Y takes 32 days to finish the work. Calculate how many days Y take to complete the piece of work: (1) 32 days (2) 10 days (3) 30 days (4) 40 days
Summary:
Total number of days taken by Y to complete the piece of work alone is 40 days.
visual curriculum