A takes 6 days less than the time taken by B to finish a piece of work. If both A and B together can finish it in 4 days, how many days will B take to finish the work?
We will use the concept of work done to solve this question.
Answer: A takes 6 days less than the time taken by B to finish a piece of work. If both A and B together can finish it in 4 days, then B takes 12 days to finish the work.
Let's assume B takes x days to finish the work. We get the quadratic equation in terms of x and we will solve the equation.
Explanation:
Suppose B alone takes x days to finish the work. Then A alone can finish it in (x−6) days
Now A's one day's work + B's one day's work = 1/x + 1/(x - 6) and (A + B)'s one day's work = 1/4
1/x + 1/(x - 6) = 1/4
⇒(x − 6) + x / x(x - 6) = 1/4
⇒ (2x - 6)/(x2 - 6x) = 1/4
⇒ 4(2x - 6) = 1(x2 - 6x)
⇒8x − 24 = x2 − 6x
⇒x2 − 14x + 24 = 0
⇒x2 − 12x − 2x + 24 = 0
⇒(x − 12) (x - 2) = 0
⇒x = 12 or x = 2, but x cannot be less than 6.
So, x = 12
Therefore, B can finish the work in 12 days.
Math worksheets and
visual curriculum
visual curriculum